New announcement. Learn more

Timeline

Date


What happened...


May 2012

Leader of SCC (David Hodge) promises new centre before old one closed.


2013 - 2015

Progress being made re Lower Road Recreation Ground (LGGR)


2015 - 2019

Delays due to personnel changes and new options being considered


Jun 2019

Old centre closed by SCC due to poor roof condition


Feb 2021

Leader of SCC (Tim Oliver) confirms budget of £2.5m to build new centre at LRRG


May 2021

Outline Planning agreed for 2-storey building at LRRG (now expired)


Apr 2022

SCC/ MVDC agree terms of ground lease at LRRG


Sep 2022

Costs increased so only single storey building possible


2023

Apparent issues re ground lease and redevelopment of old site.


Feb 2024

Leaders of SCC & MVDC round table meeting with stakeholders clarifies issues


Apr 2024

Stakeholders sign off RIBA 3


Sep 2024

Requests for information etc from SCC to support planning application for November. 


Oct 2024

Advised requires Cabinet approval to go to planning due in December


Nov 2024

More information requested for Cabinet approval now due in January 2025


Dec 2024

BYCA , BRA & LYO provide a comprehensive Stakeholder briefing for SCC – 11 pages


Feb 2025

Nothing to Cabinet but pre planning papers being drafted – more information requested by SCC.


Apr 2025

Planning refused for LLRG citing green belt and bio diversity net gains.


May 2025

Aim to revert to 164 Lower Road- demolish building and build new facility.


October 2025

Demolition of old building to start. Expected to take six weeks to complete